M/s N.V.G Constructions, v. The State of Andhra Pradesh
Case brief
What is this about?
Contractor's writ for release of withheld final-bill dues; mandamus for non-payment of admitted amount Rs.14,35,630 (gross Rs.15,81,142) under FMS No.2024-173538; Panchayat Raj CC road work, Agreement No.456/2023-24, Baireddipalle Mandal, Chittoor; Executive Engineer written instructions admitting liability; PAO bill upload; delay in payment by State arbitrary; interest on delayed payment - contractual clause binding, default 6% per annum per W.A.No.724 of 2021 and batch (12.10.2023), three-month compliance window; reliance on W.P.No.10038 of 2021 and batch (05.10.2021); Articles 226, 14, 16, 19, 300-A; disposed by Venkateswarlu Nimmagadda, J. on 12.08.2025.
What did the court decide?
Direction to the respondents to release Rs.14,35,630/- to the petitioner; where the agreement contains no interest clause, interest @ 6% per annum on the delayed payment (any contractual interest clause otherwise binding), payable if not paid within three months; liberty to pursue higher interest in an appropriate forum; no order as to costs; pending Miscellaneous Petitions stand closed