Ananda Constructions v. the State of Ap
Writ Petition (Article 226) – Release of admitted contractual dues – Mandamus
Case brief
What is this about?
Ananda Constructions v. State of A.P. (WP No.17892 of 2025, decided 21.08.2025, K. Sreenivasa Reddy, J.). Keywords: Samagra Shiksha; ZPHS Penumuru; Chittoor; government contractor; writ of mandamus; Article 226; Articles 14, 21, 300-A; release of pending amount Rs.30,29,056/-; finalized bills Rs.77,66,208/-; six weeks; interest @ 6% per annum; Treasury ID 2024-511220; Fund Transfer Order; M Book 157/A/19-20; WP No.29077 of 2018. Relevant for enforcement of admitted/uncontested payments due to contractors of the School Education/Samagra Shiksha establishment and for delayed release of finalized bills with interest consequences.
What did the court decide?
Writ petition disposed of with a direction to the respondents to release the pending amount of Rs.30,29,056/- within six (6) weeks from receipt of a copy of the order, failing which the petitioner may claim interest @ 6% per annum from the date of order till realization; no order as to costs; miscellaneous petitions, if any, stand closed.