Divikolu Subbarao v. the State of Andhra Pradesh
Case brief
What is this about?
Andhra Pradesh High Court, Amaravati; Subba Reddy Satti, J.; WP No. 1556 of 2025 (decided 11.07.2025); writ of mandamus under Article 226; APCPDCL agricultural service connections; installation of transformers; installation charges collected but connection not released; applications/payments May 2023 and March 2024; representations 07.10.2024, 04.11.2024, 13.11.2024; shortage of 11 KV discs, metal parts, PM insulators, fuse sets at district stores Ongole; disposal at admission with consent; time-bound direction to release power supply within two months; no costs; Section 151 CPC interim application closed; Articles 14, 21, 300-A invoked in the prayer; Mamillapalli Village, Santhamaguluru Mandal, Bapatla District.
What did the court decide?
Direction to Respondent Nos. 4 to 7 to release the power supply to the petitioners by following the procedure under law, within two (02) months from the date of receipt of the order; no order as to costs; pending miscellaneous petitions closed.