M/s. C. Eswara Reddy and Co, v. the State of Andhra Pradesh
Case brief
What is this about?
Andhra Pradesh High Court, Amaravati; W.P. No.13917 of 2024; Justice Subba Reddy Satti; writ of mandamus; release of pending final bills; contractor payment claims; money claim maintainable in writ jurisdiction; non-payment of admitted dues arbitrary; M/s Utkal Highways Engineers and Contractors v. Chief General Manager & Ors, SLP (C) No.14350/2022 para 8; CFMS bill fund clearance Finance Department; fresh bill on budget release; six months payment directive; R&B roads YSR Kadapa; NH 18 road widening and strengthening Km 8/0 to 18/0; Agreement CR.No./2021-22 dated 02.08.2021; Articles 14 and 21; Article 226; Section 151 CPC; disposed at admission stage with consent; no order as to costs.
What did the court decide?
Direction to the respondents to pay the amount payable to the petitioner for the executed road work within six (06) months from the date of receipt of the copy of the order; no order as to costs; pending miscellaneous petitions, if any, stood closed as a sequel.