Battula Ramanamma v. the State of Andhra Pradesh
Case brief
What is this about?
Contractor completed irrigation repair works in Banaganapalli and Sanjamala Mandals under the 'Neeru-Chettu' programme, but bill amounts were withheld without reason despite an interim payment order. The Court directed respondents to pay with 6% interest within six weeks, reserving liberty to claim differential amounts or higher interest elsewhere.
What did the court decide?
Respondents directed to pay withheld bill amounts with 6% per annum interest within six weeks; liberty to agitate differential amount/higher rate of interest before appropriate forum; no costs.