Nas Babu Constructions Pvt. Ltd. v. the State of Ap
Case brief
What is this about?
In a writ petition challenging the non-payment of admitted construction bills, the High Court directed respondents to release the claimed amount of Rs. 1,86,12,109/- along with 6% interest within three months, noting the decision was pending audit clearing.
What did the court decide?
Release of Rs. 1,86,12,109/- along with 6% per annum interest within three months.