M/s. Sri .Sai Teja Projects Pvt. Ltd, v. The State of Andhra Pradesh
Case brief
What is this about?
Petitioner challenged the demand for a premium amount of Rs.40,30,000 insisted upon by the 4th respondent for granting a quarry lease. The Court held that the petitioner must comply with the amended Minor Mineral Concession Rules via G.O.Ms.No.65 dated 04.08.2021 and directed the respondents to permit lease execution within two months.
What did the court decide?
Directing respondents to permit petitioner to execute Quarry Lease subject to complying with all conditions required as per law within two months.