Mule Rameswara Reddy, v. The State of Andhra Pradesh
Case brief
What is this about?
The petitioner, awarded a contract for water conservation works, filed a writ petition demanding payment of Rs.16.57 lakh. The Court directed respondents to complete bill verification within three weeks and pay dues within six weeks, leaving interest claims for a separate forum.
What did the court decide?
Direction to respondents to complete verification of the final bill within three weeks and pay amounts due within six weeks. Petitioner to separately claim interest for an appropriate forum.