M/S Pramod Kumar Gupta (Thekedar) Thru.Partner Abhishek Kumar Gupta v. State of U.P. Thru. Addl. Chief Secy. Deptt. of Agriculture Civil Sectt. Lko. and 3 Others
Case brief
What is this about?
Stop-work order 18.02.2026; rival contractors' complaints; contract subsists, not cancelled; inquiry pending; damages claimable for stoppage if complaints found baseless and work resumed; direction to Chief Engineer, Rajya Krishi Utpadan Mandi Parishad, U.P. to decide complaints by reasoned and speaking order with expedition; writ petition disposed; Mandi Parishad tender; U.P. Agriculture Department; Allahabad High Court Lucknow Bench; Alok Mathur J.; Amitabh Kumar Rai J.
What did the court decide?
Direction to respondent no. 3 - Chief Engineer, Rajya Krishi Utpadan Mandi Parishad, U.P., Krishi Bhawan, Lucknow to pass necessary orders on the complaints made against the petitioner by means of a reasoned and speaking order in accordance with law, with expedition. ¶18