Keshav and 3 Others v. State of U.P. and 3 Others
Case brief
What is this about?
Allahabad High Court; WRIT - C No. 22972 of 2021; Keshav v. State of U.P.; Mathura Vrindavan Development Authority; compensation for bhumidhari land; District Level Committee; Government Order dated 12.05.2016; Gata No. 825D; Gata No. 687; Gata Nos. 825 and 877; Nahar Bamba (drainage channel); representation dated 26.07.2021; mandamus; fresh representation; finalise within two months; Gopal Prasad v. State of U.P., Writ-C No. 32548 of 2019; Mahesh Chandra Tripathi, J.; Kunal Ravi Singh, J.
What did the court decide?
Liberty to the petitioners to make a fresh representation along with true attested copy of the order before the District Level Committee constituted under the Government Order dated 12.05.2016 within two weeks; the Committee to consider the claim and finalise the proceeding expeditiously, preferably within two months.