Guddu Saifi and 5 Others v. State of U.P. and Another
Case brief
What is this about?
Section 528 BNSS; Allahabad High Court; Saurabh Srivastava, J.; compromise dated 26.9.2025; verification of compromise pending; Additional Chief Judicial Magistrate-I, Muzaffar Nagar; direction to verify compromise within four weeks in presence of both parties; adjudication on basis of verification report; Registrar (Compliance); service of order within three working days; list week commencing 9.3.2026; order dated January 21, 2026.
What did the court decide?
Directions issued: the Additional Chief Judicial Magistrate-I, Muzaffar Nagar to verify the compromise within four weeks in the presence of both parties and report; Registrar (Compliance) to ensure service of the order within three working days and place the verification report on record; matter listed in the week commencing 9.3.2026. ¶¶13