Shri Balaji Enterprises v. State of U.P. and 3 Others
Case brief
What is this about?
Allahabad High Court WRIT-C 40498 of 2025, disposed 19-11-2025, bench Arindam Sinha & Satya Veer Singh JJ.; petitioner Shri Balaji Enterprises (contractor) unpaid bills Rs. 30,37,235 for executed work; respondent no. 3 Nagar Nigam; counsel Sudhanshu Kumar Gour Hari, D.K. Tiwari (Addl. CSC), Shyam Mani Shukla; work orders allegedly not annexed to writ petition; directions to communicate certified copy, work orders, unpaid bills and internal communications; verification of payable amount within three weeks with reference to internal communications; sanction and disbursement thereafter; petition disposed of, no statute or precedent cited.
What did the court decide?
Writ petition disposed of with operative directions: petitioner to send certified copy of the order with relevant work orders, unpaid bills and internal communications to respondent no. 3; respondent no. 3 to verify the payable amount within three weeks with reference to the disclosed internal communications, followed promptly by sanction and disbursement.