Binod Kumar Gupta v. C.B.S. International Project Pvt. Ltd. Thru. Director
Case brief
What is this about?
RERA Appeal 196 of 2025; Allahabad High Court Lucknow; Section 58 U.P. RERA Act 2016 appeal; Section 12 Real Estate (Regulation and Development) Act 2016; change of floor upper ground floor to first floor; brochure/prospectus commitment; allotment letter; NOIDA World-I scheme; road facing unit premium; provisional allotment letter three years possession; ex parte report before Tribunal; sanctioned map 24.07.2014 vs brochure May 2014; U.P. Real Estate Appellate Tribunal Appeal 213/2023 order 26.09.2025; admission, notice, counter affidavit four weeks; interim reservation of ground floor shop/unit; substantial questions of law; Syed Qamar Hasan Rizvi; December 5, 2025.
What did the court decide?
Appeal admitted; notice issued to the respondent, returnable at an early date; steps for service within seven working days; respondent to file counter affidavit within four weeks; appellant to file rejoinder affidavit two weeks thereafter; appeal listed in the week commencing 2nd February, 2026. As interim protection, one shop/unit on the ground floor to be kept reserved for the appellant, if still available, until the next date of listing.