State of U.P. Thru. Prin.Secy. Public Works Deptt. Secrt. Lko. and Others v. M/S Shanti Construction Thru. Its Partner Sh. Ramesh Kumar Agrawal
Case brief
What is this about?
The High Court dismissed an appeal regarding a Section 34 petition filed under the Arbitration and Conciliation Act. The court held the petition was barred by limitation because the time spent in a wrong forum was excluded under Section 14, and the subsequent filing exceeded the statutory period under Section 34(3).
What did the court decide?
The appeal was dismissed as the petition under Section 34 was barred by limitation.