Narendra Singh v. Sunil Chandra, Executive Engineer, Dakshinanchal, Vidhut Vitran Nigam Sub Division III and Another
Case brief
What is this about?
This application was filed under Section 12 of the Contempt of Courts Act for willful disobedience of a writ order dated 05.07.2023. The court did not issue a notice but granted the opposite party three months further time to comply.
What did the court decide?
The opposite party was granted three months further time to comply with the order dated 05.07.2023 in Writ C No. 16194 of 2023.