Girandra Singh v. State of U.P. and 4 Others
Case brief
What is this about?
The High Court directed the respondent authority to consider the petitioner's pending representation regarding the installation of an electric tower on his land and decide it within six weeks, rejecting the claim for immediate injunction against installation which must await the outcome of the representation process.
What did the court decide?
Direction to respondent No. 5 to decide the pending representation dated 12.3.2020 within six weeks.