Arun Kumar v. Union of India and 3 Others
Case brief
What is this about?
Writ petition challenging Section 127(2) of the Electricity Act, 2003 as unconstitutional and seeking quashing of a recovery certificate. Court held the only remedy is an appeal under Section 127 despite the time bar, directing the appellate authority to decide on merits within two months.
What did the court decide?
Petitioner directed to file appeal within 15 days; appellate authority to decide on merits within two months without considering limitation.